Program Resource Distribution Table |
ACAT I-II Level Programs
-
All contracts, subcontracts, government-performed efforts, and major components (e.g., government furnished equipment), including foreign military sales (FMS) and programs in sustainment, regardless of acquisition phase and contract type, including non-Federal Acquisition Regulation (FAR) agreements, valued at more than $50 million, then-year dollars, for ACAT I-II level programs.
-
High-risk or high-technical-interest, as determined by the CSDR plan approval authority, or software contracts priced between $20 million and $50 million, then-year dollars.
|
Contractor Cost Data Report |
ACAT I-II Programs
-
All contracts, subcontracts, government-performed efforts, and major components (e.g., government furnished equipment), including FMS and programs in sustainment, regardless of acquisition phase and contract type, including non-FAR agreements, valued at more than $50 million, then-year dollars, for current and former ACAT I – II programs.
-
High-risk or high-technical-interest, as determined by the CSDR plan approval authority, or software contracts priced between $20 million and $50 million, then-year dollars.
Information System (IS) Programs
-
All contracts, subcontracts, government-performed efforts, and major components (e.g., government furnished equipment), regardless of acquisition phase and contract type, including non-FAR agreements, valued at more than $50 million, then-year dollars, for IS programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures.
-
High-risk or high-technical-interest, as determined by the CSDR plan approval authority, or software contracts priced between $20 million and $50 million, then-year dollars.
Middle Tier Acquisition Programs
-
All contracts, subcontracts, government-performed efforts, and major components (e.g., government furnished equipment), regardless of
acquisition phase and contract type, including non-FAR agreements, valued at more than $20 million, then-year dollars, for Middle Tier Acquisition Programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures.
Other Programs in an amount greater than $100 million:
-
May be required at the discretion of the CSDR approval authority for all high interest or high risk contracts, subcontracts, or government-performed efforts.
Not required under the following conditions:
-
Contracts on programs with anticipated acquisition expenditures less than $100 million, then-year dollars.
-
Contracts priced below $20 million, then-year dollars.
-
PM requests and obtains approval from the DDCA for a reporting waiver (e.g., procurement of commercial systems).
|
Software Resources Data Report |
Development and Enterprise Resource Planning Efforts
-
All contracts, subcontracts, and government-performed efforts, regardless of acquisition phase and contract type, including non-FAR agreements, for developing and/or producing software valued at more than $20 million, then-year dollars, for:
-
Programs that exceed the ACAT I-II level thresholds.
-
IS programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures.
-
Middle Tier Acquisition Programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures.
-
High-risk or high-technical-interest software efforts estimated below $20 million, then-year dollars, as determined by the CSDR plan approval authority, if the overall effort inclusive of non-software efforts exceeds $20 million, then-year dollars.
Maintenance Efforts
-
For all contracts, subcontracts, and government-performed efforts, regardless of acquisition phase and contract type, including non-FAR agreements, for:
-
Programs with previous SRDR development or enterprise resource planning requirements or software maintenance efforts of more than $20 million, then-year dollars.
-
Programs that exceed the ACAT I-II level thresholds.
-
IS programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures.
|
Contractor Business Data Report |
-
Required for contractor business entities (e.g., plant, site, or business unit) responsible for contracts or subcontracts with CSDR requirements that are expected to exceed $250 million, then-year dollars.
-
Not required for business units based solely on CSDR requirement Middle Tier Acquisition Program contracts.
|
Maintenance and Repair Parts Data Report |
All sustainment contracts, government-performed efforts, and major components (e.g., government furnished equipment), regardless of contract type, including non-FAR agreements, valued at more than $50 million, then-year dollars, for programs that exceed ACAT I-II level thresholds and IS programs that are anticipated to exceed $100 million, then-year dollars, when equivalent information cannot be provided by the program manager, at the discretion of the CSDR plan approval authority.
|
Technical Data Report |
All contracts, government-performed efforts, and major components (e.g., government furnished equipment), regardless of acquisition phase and contract type, including non-FAR agreements, valued at more than $50 million, then-year dollars, for programs that exceed the ACAT I and II level threshold and IS programs anticipated to exceed $100 million, then-year dollars, in acquisition expenditures when equivalent information cannot be provided by the program manager, at the discretion of the CSDR plan approval authority.
|